Projects

23

Jan
2014

We have received word from the Goleta Water District that there will be a planned water shut off next Tuesday, January 28, 2014 at the West Campus Apartments. All water (hot and cold) will be disrupted between the hours of 8am and 5pm.  We are expecting this outage to affect all apartments; however it is possible that some apartments...

18

Jan
2014

What’s happening at the Sierra Madre Villages construction site this week:

The contractor will be laying sewer and water lines, as well as pouring slabs for the next 7-10 days. All work will occur within the site boundaries.

Planned disturbances for this week:

No planned disturbances this week. Fencing...

17

Jan
2014

Part of the exciting and innovative work being put into the construction of Sierra Madre Villages includes the goal of achieving certification through the LEED green building rating system. From day one, beginning with site clearance through the time we open and welcome new residents, there are actions taking place to ensure that...

16

Jan
2014

What’s happening at the Sierra Madre Villages construction site this week:

The first few months at the Sierra Madre Villages construction site have been productive! Site grading is complete, and the foundation is being poured. Walls are beginning to go up for Building 7 (12 month staff/faculty leases) on the north parcel....

06

Jan
2014

As you may have already noticed, a new UCSB Housing Project is underway on Storke Road near the West Campus Apartments. The Sierra Madre Apartments will provide housing for 515 students in 115 apartments that will be double occupancy 3-bedroom, 2-bedroom and 1-bedroom apartments. The remaining 36 units will use the same unit types,...