Projects

14

Apr
2014

PLEASE NOTE:
• With the construction activity and narrow fence line on both the North and West sides of the West Campus complex, traffic has been restricted to 1-way only on ALL parts of the perimeter road, including the stretch between Lot 2 and the entrance. 

What’s happening at the Sierra Madre Villages...

07

Apr
2014

What’s happening at the Sierra Madre Villages construction site this week:

Exciting progress continues at building 7 on the north side of the Sierra Madre construction site.  Steel frames for balconies went up last week, and prefabricated walls are expected to go up this week, going from foundation to...

01

Apr
2014

What’s happening at the Sierra Madre Villages construction site this week:

The foundation has been poured on Building 7 (at the northern portion of Sierra Madre), and the framing is now up for the balconies on that building.  The steel frames were pre-fabricated offsite, and installed in just a day!

Paving will...

27

Mar
2014

Update: West Campus/Sierra Madre Court Entrance Relocation and Storm Drain Installation

Note: the start date for paving has changed to Monday, 3/31/14

Starting on Friday, 3/28/14 Monday, 3/31/14, and continuing into next week, paving will begin for the new entrance at...

21

Mar
2014

PLEASE NOTE: This is early information we are receiving about upcoming work.  We will post an update on Monday, 3/24/14, with additional information as we receive it.

What’s happening at the Sierra Madre Villages construction site this week:

West Campus/Sierra Madre...

21

Mar
2014

We have received word from the Goleta Water District that there will be another planned water shut off next Wednesday, March 26, 2014, at the West Campus Apartments. All water (hot and cold) will be disrupted between the hours of 8am and 5pm, and all apartments in the complex will be affected.  This water shut off is due to...

20

Mar
2014

Any construction related requests for apartment transfers can be directed to the Assignment Services Office at 805-893-4021.

17

Mar
2014

What’s happening at the Sierra Madre Villages construction site this week:

The current focus of the construction project continues to be the West Campus/Sierra Madre Court entrance relocation and storm drain installation.  There will be continued activity at the corner of the 710 building as Tierra Construction installs a...

14

Mar
2014

We have received word from the Goleta Water District that there will be planned water shut off next Tuesday, March 18, 2014, at the West Campus Apartments. All water (hot and cold) will be disrupted between the hours of 8am and 4pm.  At this point in time it appears that the outage will be limited to apartments on the north side of...

14

Mar
2014

Good Morning West Campus!

We have just heard from the Sierra Madre contractors that there will be continued work on the storm drain project today.  They are currently working to bring the storm drain across the entrance road, which will result in a few short, 5 minute road closures between building 710 and Lot 2 as equipment is...