As part of the 12kV project, construction work will be done in the storage yard in the south west corner of El Colegio and Storke/Slough Rd (see image). Digging will commence tomorrow for the installation of a manhole. The work is expected to be completed by Friday, June 20th. The crews are authorized to work between 7am...
Projects
Jun
2014
Jun
2014
12kV Backbone Project
This week, we are coming up on the portion of construction that will impact the bike path along El Colegio Rd. The work will take place between the Santa Ynez Apartments entrance and Camino Corto. Crews will be excavating and doing vault placement in this area. The bike path will be closed while work...
Jun
2014
12kV Backbone Project
The 12kV backbone project will bring electrical infrastructure from the UCSB main campus, through Santa Ynez Apartments out to Storke Rd, and terminate near West Campus Family Student Housing. This will result in energy cost savings for the University and allow for more control from future increases....
May
2014
What’s happening at the Sierra Madre Villages construction site this week:
Paving at the new West Campus/Sierra Madre Court and Storke road entrance has been completed. All traffic entering/exiting the complex has been transitioned to the new road. Work continues on either side of the road, adding sidewalks...
Apr
2014
What’s happening at the Sierra Madre Villages construction site this week:
Paving at the new West Campus/Sierra Madre Court entrance has been completed. All traffic entering/exiting the complex will be transitioned to the new road on the morning of Wednesday, April 30th. Workers will be on site...
Apr
2014
The new entrance at West Campus is now paved and ready for use! The transition from the old entrance to the new entrance will occur tomorrow morning, Wednesday, April 30th. Fencing will be changed to eliminate confusion between the old and new entrance, and the workers will be on site directing traffic as the change is...
Apr
2014
We have received word from the Goleta Water District that there will be a planned water shut off next Thursday, May 1, 2014, at the West Campus Apartments, on the south side of the complex. All water (hot and cold) will be disrupted between the hours of 8am and 5pm in the buildings listed below.
This disruption will...
Apr
2014
What’s happening at the Sierra Madre Villages construction site this week:
Paving at the new West Campus/Sierra Madre Court entrance is expected to finish around April 24th. Once the road is completed traffic will be shifted to the new entrance. We will notify residents of the new traffic pattern...
Apr
2014
We have received word from the Goleta Water District that there will be a planned water shut off next Wednesday, April 23, 2014, at the West Campus Apartments. Given that West Campus has encountered several water shut offs in the past months, GWD is doing everything possible to minimize the impact to residents. Work will occur...