Projects

16

Mar
2015

The San Joaquin Apartments construction project continues to work on the site grading, with heavy earth-moving equipment mixing and compacting soil to prepare for the new building foundations. The new parking lot across Storke Road is also scheduled to be complete by the end of Spring Quarter.

With the Spring Break period...

26

Feb
2015

We are happy to announce that the Storke Exterior Renovation Project is scheduled to begin in early March. This project will repair exterior building components that are beyond typical maintenance and need to be replaced to mitigate water intrusion and prepare the complex for future painting. We do not anticipate that the contractor...

13

Feb
2015

A paving contractor is scheduled to patch asphalt along the north curb and gutter of Sierra Madre Court this coming Monday (2/16) from 8:30-11:30am. Traffic control will be provided so that residents of West Campus Family Student Housing can enter and exit the complex at all times. Once this work is complete the construction fence at...

10

Feb
2015

Construction crews will be trenching across Parking Lot 1 and the lawn area between West Campus Family Student Housing Building 706 and 703 starting Thursday (2/12) thru Wednesday (2/18) to bring electrical and communication services to the new parking lot. The contractor plans to perform a majority of the parking lot trenching...

06

Feb
2015

Wondering what's going on near the Santa Cruz Residence Hall basketball court? After next week, this area will be home to a new outdoor exercise area with a variety of equipment. During the one-week installation, one of the two basketball courts will be used, as well as a few parking spots in Lot 2. Thank you to the students who...

28

Jan
2015

The San Joaquin project is moving along quickly with the excavation for underground utilities on the main project site, as well as rough grading for the new parking lot west of Storke Road. The project team will be working on creating additional temporary handicapped parking directly outside the North Tower lobby this week, which...

26

Jan
2015

The southwest corner of the perimeter road at West Campus Family Student Housing (see photo) will be closed Monday (1/26) through Wednesday (1/28) for asphalt repairs. In addition, a small area in Parking Lot #3 as well as a patch at the main road entrance off Storke Road will be patched on Wednesday (1/28) to take advantage of the...

23

Jan
2015

The contractor working on the KITP residential project is currently in the process of installing a dewatering system that will pump out water from the ground beneath the construction site.  This system has to be operational before our next storm comes in, and despite their efforts, they will not be able to complete the work by Friday...

15

Jan
2015

A section of bike path south of the KITP residence construction site will be closed on Friday, January 16 starting at 7:30am and should be re-opened by 9:30am.  The contractor working on the project will be installing dewatering lines along this southern edge during this time.  Please feel free to email campus representative...

15

Jan
2015

The San Joaquin Apartments project started construction over winter break, and in less than 4 weeks the contractor has set up all the construction fencing, temporary parking, and is nearly complete with the removal of the asphalt parking lots and surrounding hardscape. The project team is collaborating together to address any site...