Projects

30

May
2017

The new 6-story apartments at the West end of the site are nearing completion, and one of the primary activities remaining is the verification and testing of the life safety systems. This testing requires the fire alarm horns and strobes to be operated for short periods of time, and will continue intermittently through June 9th until...

14

Apr
2017

We are excited to share that the contractor has completed the North Village apartments that include Elsinore Court, Calaveras Court, Malibu Court, and Ramona Court. Ramona Court has been occupied since Fall quarter and Malibu Court has been partially occupied since Spring Break. The construction project team will now shift their focus...

06

Apr
2017

Due to some unforeseen grading and elevation issues, the roadwork along the east end of Storke Road between El Colegio Road and Sierra Madre Court has been delayed a few weeks. However, the project team has implemented creative solutions and have scheduled the paving patch back for April 24th. This paving effort will include the new...

14

Mar
2017

The new 3-story apartments at the North end of the San Joaquin site are nearing completion, and one of the primary activities remaining is the verification and testing of the life safety systems. This testing requires the fire alarm horns and strobes to be operated for short periods of time, and will continue through the remainder of...

03

Mar
2017

Starting Monday, March 6th, the road contractor will shift the focus of their work to the sidewalk replacement along the east end of Storke Road from El Colegio Road to Sierra Madre Court. This work will take approximately 8-weeks to complete, and will partially include some of the San Joaquin project site, including a new bus turnout...

21

Feb
2017

In preparation for opening the next set of San Joaquin apartments (Malibu Court), several large trailer trucks are scheduled to deliver furniture, appliances, and equipment today (2/21) through next Friday (3/3). Construction personnel will be unloading these trucks along the North Loop service road (see red area on site map) and...

12

Dec
2016

To take advantage of the winter break period while a majority of our residents are away, the San Joaquin project team has scheduled a significant amount of work that is detailed below:

  • Underground gas line connections for new buildings will require a gas outage of Ramona Court this coming Monday, 12/12, between the hours...
18

Nov
2016

As a result of community input, UCSB, Santa Barbara County, and the traffic engineering project team have completed the design modifications of the El Colegio & Storke Road intersection to add enhanced safety measures. Starting Monday, November 21st, the contractor will resume working on the southeast corner closest to Isla Vista...

03

Nov
2016

The North Loop Bike Path at Santa Catalina & San Joaquin Apartments will be closed next week Nov. 7th – Nov. 18th to allow the contractor to finish installing the permanent light poles. Residents of Santa Catalina & San Joaquin will still have access to the bike parking by traveling down the access road as usual, but residents...

01

Nov
2016

Please be advised that fire alarm testing for the next two clusters of apartments north of Santa Catalina residence hall and west of San Joaquin Ramona Court apartments is scheduled to start Friday, November 4th, and will continue through the end of next week. During this critical life safety testing, fire alarm horns will be...

Pages