San Joaquin Apartments

Project Blog posts tagged with San Joaquin Apartments

03

Nov
2016

The North Loop Bike Path at Santa Catalina & San Joaquin Apartments will be closed next week Nov. 7th – Nov. 18th to allow the contractor to finish installing the permanent light poles. Residents of Santa Catalina & San Joaquin will still have access to the bike parking by traveling down the access road as usual, but residents...

01

Nov
2016

Please be advised that fire alarm testing for the next two clusters of apartments north of Santa Catalina residence hall and west of San Joaquin Ramona Court apartments is scheduled to start Friday, November 4th, and will continue through the end of next week. During this critical life safety testing, fire alarm horns will be...

25

Jan
2016

Construction is moving along quickly for the entire San Joaquin project! One of the two new 6-story Towers will have the concrete roof deck poured by the end of February, and the second 6-story Tower is scheduled to top out by the end of March. The project currently has two separate cranes working on-site, with one crane loading...

02

Nov
2015

We are very excited to see the structures of the San Joaquin project start to rise up around Santa Catalina! Two of the four wood-framed Villages along the north end of the site will be completely framed out by December 2015, and crews are working hard to close in as many buildings as possible before the inclement winter weather...

29

May
2015

Due to supplier issues with the large concrete pour scheduled for next Tuesday (6/2), the contractor will need to split the pour into two days… still Tuesday (6/2) but also again on Wednesday (6/3). The positive outcome from this change is that the contractor will be able to start 1-hour later in the morning. Instead of 5:00am,...

21

May
2015

We have some very exciting work activities and changes to the site scheduled for this next week at the San Joaquin project! The contractor has completed paving the new East Access Road (see photo) and is currently working on the final connection to El Colegio Road. This access road will serve as the primary vehicle access to ADA...

15

May
2015

We are excited to update our H&RS community that the contractor is nearing completion of the new parking lot 60 to the west of Storke Road, with only irrigation, landscaping, site lighting, and asphalt striping remaining. The most recent schedule from the contractor shows the new lot being fully complete and ready for the...

16

Mar
2015

The San Joaquin Apartments construction project continues to work on the site grading, with heavy earth-moving equipment mixing and compacting soil to prepare for the new building foundations. The new parking lot across Storke Road is also scheduled to be complete by the end of Spring Quarter.

With the Spring Break period...

28

Jan
2015

The San Joaquin project is moving along quickly with the excavation for underground utilities on the main project site, as well as rough grading for the new parking lot west of Storke Road. The project team will be working on creating additional temporary handicapped parking directly outside the North Tower lobby this week, which...

15

Jan
2015

The San Joaquin Apartments project started construction over winter break, and in less than 4 weeks the contractor has set up all the construction fencing, temporary parking, and is nearly complete with the removal of the asphalt parking lots and surrounding hardscape. The project team is collaborating together to address any site...