January, 2015 Blog Posts

28

Jan
2015

The San Joaquin project is moving along quickly with the excavation for underground utilities on the main project site, as well as rough grading for the new parking lot west of Storke Road. The project team will be working on creating additional temporary handicapped parking directly outside the North Tower lobby this week, which...

26

Jan
2015

The southwest corner of the perimeter road at West Campus Family Student Housing (see photo) will be closed Monday (1/26) through Wednesday (1/28) for asphalt repairs. In addition, a small area in Parking Lot #3 as well as a patch at the main road entrance off Storke Road will be patched on Wednesday (1/28) to take advantage of the...

23

Jan
2015

The contractor working on the KITP residential project is currently in the process of installing a dewatering system that will pump out water from the ground beneath the construction site.  This system has to be operational before our next storm comes in, and despite their efforts, they will not be able to complete the work by Friday...

15

Jan
2015

A section of bike path south of the KITP residence construction site will be closed on Friday, January 16 starting at 7:30am and should be re-opened by 9:30am.  The contractor working on the project will be installing dewatering lines along this southern edge during this time.  Please feel free to email campus representative...

15

Jan
2015

The San Joaquin Apartments project started construction over winter break, and in less than 4 weeks the contractor has set up all the construction fencing, temporary parking, and is nearly complete with the removal of the asphalt parking lots and surrounding hardscape. The project team is collaborating together to address any site...

14

Jan
2015

The contractor working on the KITP residential project is doing some hydro excavation this week and part of next.  In order to complete this portion of the project on time, the contractor will need to work on Saturday, January 17.  They will be on-site starting at 8am and work until about 4pm.  Hydro excavation involves using high...

13

Jan
2015

The Club renovation project is utilizing a portion of parking lot 23 for construction staging. In order to increase safety for cyclists and pedestrians, the bike path is being rerouted to the west of the staging area. This will allow construction vehicles to move between the staging area and the construction site without having to...