2014

Three of the five residential buildings on the main site are fully framed out, with the pre-fabricated walls and roof trusses completed and two of the buildings starting to have roofing and windows installed. A model unit is scheduled to be completed by the end of December. We are looking forward to installing all the appliances and...

12

Nov
2014

The construction company will be doing noisy asphalt demo work this Wednesday morning, 11/12/14, starting at 7am in Lot 53.   We have asked them to not start the noisiest of the work until after 8am.

Please feel free to email Ray.Aronson@dcs.ucsb.edu  if additional...

08

Nov
2014

We are very excited to announce that the San Joaquin Apartments & Portola Dining Commons project will start in early January. For those of you who have yet to hear about the project, there are 3-main areas of development around Santa Catalina: