San Joaquin Concrete Pour

May 29, 2015

Due to supplier issues with the large concrete pour scheduled for next Tuesday (6/2), the contractor will need to split the pour into two days… still Tuesday (6/2) but also again on Wednesday (6/3). The positive outcome from this change is that the contractor will be able to start 1-hour later in the morning. Instead of 5:00am, concrete pumps will start at 6:00am and continuously pour concrete through 4:00pm on both Tuesday and Wednesday. We apologize for the any noise impact that this may have and appreciate your understanding during this next phase of construction.