KITP - Dewatering System Installation

January 23, 2015

The contractor working on the KITP residential project is currently in the process of installing a dewatering system that will pump out water from the ground beneath the construction site.  This system has to be operational before our next storm comes in, and despite their efforts, they will not be able to complete the work by Friday, January 23.  In order to complete the work on time, the contractor will be on site on Saturday, January 24 to continue the installation.  The work should be generally quiet.  There will be a small generator running and a forklift will be used periodically to move items. Please feel free to email campus representative Ray.Aronson@dcs.ucsb.edu if additional information about the KITP project is needed.